Description
Battery energy storage system (BESS) facility
External Link
View application on ottawa.ca
Status History
December 02, 2025:
404_missing_data
December 02, 2025:
Active
Addresses
4186 WILLIAM MCEWEN Drive Rideau
City Staff Contact
Stephan Kukkonen
stephan.kukkonen@ottawa.ca
613-580-2424 x12860
Documents
2025-12-28 - Plan of Survey
2025-12-02 - Application Summary
2025-10-31 - Typical Details
2025-10-31 - Tree Conservation Report
2025-10-31 - Transmission Line Overall Site Plan
2025-10-31 - Topographic Plan of Survey
2025-10-31 - Switchyard Site Plan Overall
2025-10-31 - Stormwater Management Report
2025-10-31 - Site Servicing Letter
2025-10-31 - Site Plan Overall
2025-10-31 - Site Plan
2025-10-31 - Sections 2
2025-10-31 - Sections 1
2025-10-31 - Retention Pond View Plan and Sections
2025-10-31 - Proposed Zoning Map 2
2025-10-31 - Proposed Zoning Map 1
2025-10-31 - Plan View Sections 2
2025-10-31 - Plan View Sections 1
2025-10-31 - Plan 4R-36965
2025-10-31 - Overall Site Pre Development
2025-10-31 - Overall Site Post Development
2025-10-31 - Overall Site Layout
2025-10-31 - Landscape Plan
2025-10-31 - Hydrogeological and Terrain Analysis Study
2025-10-31 - Hazard Mitigation Analysis
2025-10-31 - Grading and Drainage Plan
2025-10-31 - Geotechnical Investigation
2025-10-31 - General Notes
2025-10-31 - Fluvial Geomorphology Assessment
2025-10-31 - Fire Protection Location
2025-10-31 - Erosion and Sediment Control Details During Construction 2
2025-10-31 - Erosion and Sediment Control Details During Construction 1
2025-10-31 - Environmental Impact Study
2025-10-31 - Emission Summary and Dispersion Modeling Report
2025-10-31 - Civil Design Criteria
2025-10-31 - Civil Cover Page & Drawing Index
2025-10-31 - Acoustic Assessment Report
2025-08-11 - Pre-Cast Noise Wall
2025-08-11 - Planning Rationale
2025-08-11 - Landscape Plan
2025-08-11 - Hydrogeological and Terrain Analysis Study
2025-08-11 - Geotechnical Investigation and Design
2025-08-11 - Fluvial Geomorphology Assessment
2025-08-11 - Environmental Impact Study
2025-08-11 - Decommissioning Plan
2025-08-11 - Commissioning Plan
2025-08-11 - Civil - Typical Details
2025-08-11 - Civil - Standard Details
2025-08-11 - Civil - Site Plan Overall
2025-08-11 - Civil - Site Plan
2025-08-11 - Civil - Sections 2
2025-08-11 - Civil - Sections
2025-08-11 - Civil - Retention Pond View Plan and Sections
2025-08-11 - Civil - Plan View Sections 2
2025-08-11 - Civil - Plan View Sections
2025-08-11 - Civil - Overall Site Layout
2025-08-11 - Civil - Grading and Drainage Plan
2025-08-11 - Civil - General Notes
2025-08-11 - Civil - Fire Protection Location
2025-08-11 - Civil - Erosion and Sediment Control Plan During Construction
2025-08-11 - Civil - Erosion and Sediment Control Details During Construction
2025-08-11 - Civil - Cover Page and Drawing Index
2025-08-11 - Civil - Coordinates
2025-06-04 - Planning Rationale
2025-06-04 - Grading and Drainage Plan
2025-05-16 - Zoning Confirmation Report
2025-05-16 - Wetland Evaluation Data and Scoring Record
2025-05-16 - Typical Details
2025-05-16 - Tree Conservation Report
2025-05-16 - Trail Road BESS Wetland Evaluation
2025-05-16 - Traffic Assessment Study
2025-05-16 - Topographic Plan of Survey
2025-05-16 - Storm Water Management Report
2025-05-16 - Site Plan Overall
2025-05-16 - Site Plan
2025-05-16 - Sections 2
2025-05-16 - Sections
2025-05-16 - Retention Pond Views and Section
2025-05-16 - Preliminary Construction Management Plan
2025-05-16 - Planning Rationale
2025-05-16 - Plan View Sections 2
2025-05-16 - Plan View Sections
2025-05-16 - Overall Site Layout
2025-05-16 - Landscape Plan
2025-05-16 - Hydrogeological and Terrain Analysis Study
2025-05-16 - Hazard Mitigation Analysis
2025-05-16 - Geotechnical Investigation
2025-05-16 - General Notes and Legend
2025-05-16 - Fluvial Geomorphology Assessment - Rev 0
2025-05-16 - Fluvial Geomorphology Assessment
2025-05-16 - Fire Protection Location
2025-05-16 - Fence Drawing
2025-05-16 - Erosion and Sediment Control Plan
2025-05-16 - Environmental Impact Study
2025-05-16 - Emergency Response Plan
2025-05-16 - Civil Design Criteria
2025-05-16 - Civil - Coordinates
2025-12-08 - Emergency Response Plan