Application Details
Number
D07-12-21-0170
Type
Site Plan Control
Indexed
April 27, 2022
Description
Infill the existing hospital campus with a continuum of care seniors community consisting of a Long Term Care Home (256 beds) in Phase 1, and a 15-storey registered retirement home (270 beds) and shared amenity space in the second phase.
External Link
View application on ottawa.ca
Status History
April 27, 2022:
Active
December 16, 2022:
File Pending
August 16, 2023:
Active
August 16, 2023:
Inactive
Addresses
1967 RIVERSIDE Drive Old Ottawa
City Staff Contact
Tracey Scaramozzino
tracey.scaramozzino@ottawa.ca
613-325-6976
Documents
2022-04-27 - Application Summary
2022-04-27 - Tree Conservation Report
2022-04-27 - Tansley Woods Precendent Images
2022-04-27 - Site Servicing Plan
2022-04-27 - Site Grading and Drainage Plan
2022-04-27 - Shadow Study
2022-04-27 - Servicing and Stormwater Management Report
2022-04-27 - Riverside Strategy Report
2022-04-27 - Planning Rationale
2022-04-27 - Phase 1 Environmental Site Assessment
2022-04-27 - Overall Exterior Elevations
2022-04-27 - Landscape Plans
2022-04-27 - Erosion and Sediment Control Plan
2022-04-27 - Environmental Noise Control Study
2022-04-27 - Civil Plans
2022-04-27 - Campus Plan and Zoning Information
2022-04-27 - 45 Degree Angular Plane
2023-01-04 - Transportation Impact Assessment
2023-01-04 - Traffic Simulation Summaries
2023-01-04 - Site Servicing Plan
2023-01-04 - Site Grading and Drainage Plan
2023-01-04 - Servicing and Stormwater Management Report
2023-01-04 - Rail Safety Report
2023-01-04 - Phase II Environmental Site Assessment
2023-01-04 - Phase II - Evaluation of L-shaped Plan
2023-01-04 - Park Facility Fit Plan
2023-01-04 - Overall Exterior Elevations
2023-01-04 - Landscape Plan and Details
2023-01-04 - Geotechnical Investigation
2023-01-04 - Existing Conditions and Removals Plan
2023-01-04 - Erosion and Sediment Control Plan
2023-01-04 - Campus Plan and Zoning Information and Master Plan
2023-01-04 - Site Plan
2023-04-26 - Site Servicing Plan -
2023-04-26 - Site Grading & Drainage Plan
2023-04-26 - Servicing & Stormwater Management Report -
2023-04-26 - Parkette Fit Plan -
2023-04-26 - Ottawa Flow Control Roof Drainage Declaration
2023-04-26 - FUS Classification Declaration Phase 2
2023-04-26 - Flow Control Roof Drainage Declaration
2023-04-26 - EXISTING CONDITIONS & REMOVALS PLAN
2023-04-26 - Erosion & Sediment Control Plan -
2023-04-26 - Classification Declaration Phase 1
2023-04-26 - Campus & Zoning Information Map -
2023-08-09 - DELEGATED AUTHORITY REPORT SIGNED
2023-08-09 - Approved Tree Conservation Report
2023-08-09 - Approved Site Servicing Plan
2023-08-09 - Approved Site Grading and Drainage Plan
2023-08-09 - Approved Servicing & Stormwater Management Report
2023-08-09 - Approved Plan & Profiles
2023-08-09 - Approved Park Facility Fit Plan
2023-08-09 - Approved Overall Exterior Elevations EL-01 & EL-02
2023-08-09 - Approved Master Plan
2023-08-09 - Approved Landscape Plans and Details
2023-08-09 - Approved Global Stability Analysis Proposed Retaining Walls
2023-08-09 - Approved Geotechnical Investigation
2023-08-09 - Approved Existing Conditions & Removals Plan
2023-08-09 - Approved Erosion and Sediment Control Plan
2023-08-09 - Approved Campus Plan and Zoning Information Plan
2024-03-15 - Commence Work Notification - Registration of Agreement