right of way, heritage and urban design services
renovation of original house and construction of a rear addition at 119 york street, a property designated under part v of the ontario heritage act, within the byward market heritage conservation district
Report - Renovation of original house and construction of a rear addition at 119 York Street
Document 11 - Heritage Evaluation and Survey Forms 1 and 2
application to alter the medical arts building, 180 metcalfe street, a property designated under part iv of the ontario heritage act
Report - Application to alter the Medical Arts Building, 180 Metcalfe Street
Document 12 - Cultural Heritage Impact Statement
Document 13 - Heritage Ottawa Comments
Possibly related devapp: D02-02-14-0116
Possibly related devapp: D01-01-14-0021
Possibly related devapp: D09-04-18-0003
technical circulations
zoning by-law amendment proposal - 116 york street
116 York Street – Technical Circulation
Possibly related devapp: D02-02-18-0071

Votes

ITEM: Minutes 32 - Thursday, August 2, 2018

Motion Yes No Absent/Recused
Motion To:
pop-out
Motion To:
pop-out
S. Moffatt
B. Padolsky
L. A. (Sandy) Smallwood
C. Quinn
C. McKenney
T. Nussbaum
M. Wilkinson (a)

ITEM: RENOVATION OF ORIGINAL HOUSE AND CONSTRUCTION OF A REAR ADDITION AT 119 YORK STREET, A PROPERTY DESIGNATED UNDER PART V OF THE ONTARIO HERITAGE ACT, WITHIN THE BYWARD MARKET HERITAGE CONSERVATION DISTRICT

Motion Yes No Absent/Recused
Motion To: Que le Sous-comité du patrimoine bâti recommande au Comité de l’urbanisme de recommander à son tour au Conseil : 1. D’approuver la demande de démolition des annexes arrière du bâtiment situé au 119, rue York, conformément aux plans soumis par Studioworks International Inc. et datés du 4 juillet 2018; 2. D’approuver les modifications proposées à la propriété située au 119, rue York, qui consistent notamment à construire une nouvelle annexe arrière et à effectuer diverses interventions paysagères, conformément aux plans préparés par Studioworks International Inc. et datés du 4 juillet 2018, sous réserve de toute autre approbation d’aménagement; 3. De déléguer au directeur général de Planification, Infrastructure et Développement économique le pouvoir d’effectuer des modifications mineures de conception; 4. De délivrer le permis relatif au patrimoine, devant expirer dans deux ans à compter de la date de sa délivrance. (Nota : Le déla
pop-out
Motion To: WHEREAS the Applicant has submitted revised versions of the Site Plan, Elevations and Renderings on September 12, 2018 with respect to the proposed alterations and construction at 119 York Street, in response to community input; THEREFORE BE IT RESOLVED THAT report recommendations 1 and 2 be amended by replacing the date of “July 4, 2018” with “July 4, 2018 and revised September 12, 2018”; and, BE IT FURTHER RESOLVED THAT the ‘Discussion’ section of the report be amended by replacing the words “including the majority of the west façade and the two-storey front facing bay of the addition” with “and from the condominium building to the rear”; and BE IT FURTHER RESOLVED THAT the ‘Discussion’ section of the report be amended by deleting the words “that are not visible from the street, mainly the east, north (rear) and the portion of the west façade abutting the property line”; and BE IT FURTHER RESOLVED THAT Documents 2, 3, 4 and 8 of the report be
pop-out
Motion To: WHEREAS the Applicant has submitted revised versions of the Site Plan, Elevations and Renderings on September 12, 2018 with respect to the proposed alterations and construction at 119 York Street, in response to community input; THEREFORE BE IT RESOLVED THAT report recommendations 1 and 2 be amended by replacing the date of “July 4, 2018” with “July 4, 2018 and revised September 12, 2018”; and, BE IT FURTHER RESOLVED THAT the ‘Discussion’ section of the report be amended by replacing the words “including the majority of the west façade and the two-storey front facing bay of the addition” with “and from the condominium building to the rear”; and BE IT FURTHER RESOLVED THAT the ‘Discussion’ section of the report be amended by deleting the words “that are not visible from the street, mainly the east, north (rear) and the portion of the west façade abutting the property line”; and BE IT FURTHER RESOLVED THAT Documents 2, 3, 4 and 8 of the report be
pop-out
S. Moffatt
B. Padolsky
L. A. (Sandy) Smallwood
M. Wilkinson
C. Quinn
C. McKenney
T. Nussbaum
Motion To: Que le Sous-comité du patrimoine bâti recommande au Comité de l’urbanisme de recommander à son tour au Conseil : 1. D’approuver la demande de démolition des annexes arrière du bâtiment situé au 119, rue York, conformément aux plans soumis par Studioworks International Inc. et datés du 4 juillet 2018; 2. D’approuver les modifications proposées à la propriété située au 119, rue York, qui consistent notamment à construire une nouvelle annexe arrière et à effectuer diverses interventions paysagères, conformément aux plans préparés par Studioworks International Inc. et datés du 4 juillet 2018, sous réserve de toute autre approbation d’aménagement; 3. De déléguer au directeur général de Planification, Infrastructure et Développement économique le pouvoir d’effectuer des modifications mineures de conception; 4. De délivrer le permis relatif au patrimoine, devant expirer dans deux ans à compter de la date de sa délivrance. (Nota : Le déla
pop-out
S. Moffatt
B. Padolsky
L. A. (Sandy) Smallwood
M. Wilkinson
C. Quinn
C. McKenney
T. Nussbaum

ITEM: APPLICATION TO ALTER THE MEDICAL ARTS BUILDING, 180 METCALFE STREET, A PROPERTY DESIGNATED UNDER PART IV OF THE ONTARIO HERITAGE ACT

Motion Yes No Absent/Recused
Motion To: Que le Sous-comité du patrimoine bâti recommande au Comité de l’urbanisme de recommander à son tour au Conseil : 1. D’approuver la demande de modification de l’édifice Medical Arts, situé au 180, rue Metcalfe, conformément aux plans soumis par Roderick Lahey Architect Inc. le 28 juillet 2018 et ci-joints en tant que documents 3 à 7, et aux plans d’étayage préparés par REMISZ Consulting Engineers, ci-joints en tant que document 9, sous réserve des conditions suivantes : a. Suppression de l’auvent d’entrée et des marquises de fenêtres proposés et illustrés dans le document 5; b. Le requérant devra affiner davantage le projet d’éclairage illustré dans le document 7, en consultation avec le personnel responsable du patrimoine; c. Le requérant devra travailler de concert avec un spécialiste en patrimoine et en consultation avec le personnel responsable du patrimoine en vue de trouver des solutions de rechange en matière d’accessibilité unive
pop-out
S. Moffatt
B. Padolsky
L. A. (Sandy) Smallwood
M. Wilkinson
C. Quinn
C. McKenney
T. Nussbaum

Public Comment Contact Information

Everyone is entitled to attend committee meetings and provide a verbal statement (up to 5 minutes long) before Councillors vote on each agenda item. If you are not able to attend a meeting, you can also email your comments to councillors. Either way, your statements become part of the official record - and this is the single most important step to shaping the outcome of your city.

Click this "mailto:" link, or cut-and-paste the following email addresses to send your comments:

eric.pelot@ottawa.ca, catherine.mckenney@ottawa.ca, scott.moffatt@ottawa.ca, tobi.nussbaum@ottawa.ca, marianne.wilkinson@ottawa.ca

Committee Members:
Name Last Email Phone
Catherine McKenney catherine.mckenney@ottawa.ca 613-580-2484
Scott Moffatt scott.moffatt@ottawa.ca 613-580-2491
Tobi Nussbaum tobi.nussbaum@ottawa.ca 613-580-2483
Marianne Wilkinson marianne.wilkinson@ottawa.ca 613-580-2474