D07-12-18-0182

Site Plan Control: The City of Ottawa has received a Site Plan application to construct two one storey light industrial buildings. The proposal will allows for two 4,483.4 square metre one-storey buidlings. Each building will accommodate up to 3 tenants with showroom, office space and warehouse. A total of 114 parking spaces are proposed to serve both buildings and each building will have 10 loading spaces. The loading area located between the two buildings has a shared access onto Ages Drive. Trees and shrubs will be planted along Ages Drive to partially screen the large building face. View application on ottawa.ca

WardWard 10 - GLOUCESTER-SOUTHGATE - Diane Deans
Received2018-12-06
Updated2019-06-11
Address (Zoning) 899 AGES (IG3)
903 AGES (IG3)
901 AGES (IG3)
Documents
Title Modified
2019-05-10 - Approved Building Elevation BuildingA - 2019-05-10
2019-05-10 - Approved Building Elevation BuildingB - 2019-05-10
2019-05-10 - Approved Erosion and Sediment Control Plan- 2019-05-10
2019-05-10 - Approved Grading Drainage and SWM Plan - 2019-05-10
2019-05-10 - Approved Landscape Plan - 2019-05-10
2019-05-10 - Approved Servicing Plan - 2019-05-10
2019-05-10 - Approved Site Plan - 2019-05-10
2019-05-10 - Delegated Authority Report - 2019-05-10
2019-03-28- Servicing and SWM Report - 2019-03-27
2019-03-28 - Erosion Control Plan - 2019-03-27
2019-03-28 - Grading Drainage & SWM Plan - 2019-03-27
2019-03-28 - Landscape Plan - 2019-03-27
2019-03-28 - Servicing Plan - 2019-03-27
2019-03-28 - Site Plan - 2019-03-27
2019-03-06 - Building Elevations Building A - 2019-03-04
2019-03-06 - Building Elevations Building B - 2019-03-04
2019-03-06 - Phase 1 ESA - 2019-03-04
2019-03-06 - Landscape Plan - 2019-02-28
2019-03-06 - Lighting Certificate - 2019-02-28
2019-03-06 - Rendering Building 1 - 2019-02-28
2019-03-06 - Rendering Building 2 - 2019-02-28
2019-03-06 - Site Plan - 2019-02-28
2019-03-06 - Erosion Sediment Control Plan - 2019-02-22
2019-03-06 - Grading Drainage SWM Plan - 2019-02-22
2019-03-06 - Servicing Plan - 2019-02-22
2018-12-20 - Application Summary - 2018-12-20
2018-12-18 - Landscape Plan - 2018-12-05
2018-12-18 - Planning Rationale - 2018-12-05
2018-12-18 - Building Elevations Building A - 2018-11-30
2018-12-18 - Building Elevations Building B - 2018-11-30
2018-12-18 - Erosion and Sediment Control Plan - 2018-11-30
2018-12-18 - Grading Drainage & Stormwater Management Plan - 2018-11-30
2018-12-18 - Servicing and Stormwater Management Report - 2018-11-30
2018-12-18 - Servicing Plan - 2018-11-30
2018-12-18 - Site Plan - 2018-11-30
2018-12-18 - Topographic Plan - 2018-11-30
2018-12-18 - Transportation Impact Assessment - 2018-11-29
2018-12-18 - Vibration Assessment - 2018-11-27
2018-12-18 - Geotechnical Report - 2018-10-24
2018-12-18 - Phase 1 Environmental Site Assessment - 2018-10-24
2018-12-18 - Survey - 2018-07-26
Date Status
2019-06-10 Receipt of Agreement from Owner Pending
2019-05-13 Request for Agreement Received
2019-05-08 Application Approved
2019-04-29 Applicant Concurs
2019-03-22 Application File Pending
2019-03-06 Application Reactivated
2019-01-21 Application File Pending
2018-12-21 Comment Period in Progress
2018-12-13 Community Heads Up - supporting documents to be posted later during circulation period

comments powered by Disqus
Created by Kevin O'Donnell to make it easier to be part of the political conversation in Ottawa.
On Twitter? Follow @OttWatch and @ODonnell_K
Privacy Policy