D07-12-17-0176

Site Plan Control: The City of Ottawa has received an Official Plan Amendment, a Zoning Bylaw Amendment and a Site Plan Control application to facilitate the development of an 18-storey high-rise apartment building containing 228 units. View application on ottawa.ca

WardWard 22 - GLOUCESTER-SOUTH NEPEAN - Carolanne Meehan
Received2017-12-22
Updated2019-06-10
Address (Zoning) 1024 MCGARRY (MC[1441] H(62))
1012 MCGARRY (MC[1441] H(62))
Possibly related devapp(s) D02-02-17-0130 - Zoning By-law Amendment
D01-01-17-0027 - Official Plan Amendment
Possibly related by-laws 2018-269: A by-law of the City of Ottawa to amend the South Nepean Urban Area Secondary Plan, South Nepean Town Centre - Area 7 of Volume 2a of the Official Plan for the City of Ottawa for the lands municipally known as 1012 and 1024 McGarry Terrace
2018-270: A by-law of the City of Ottawa to amend By-law No. 2008-250 to change the zoning of lands known municipally as 1012 and 1024 McGarry Terrace
Documents
Title Modified
2019-02-22 - Approved Erosion Control Plan - 2019-02-22
2019-02-22 - Approved Existing Conditions Plan - 2019-02-22
2019-02-22 - Approved Floor Plan - P2 Level Parking - 2019-02-22
2019-02-22 - Approved General Elevation - East Facade - 2019-02-22
2019-02-22 - Approved General Elevation - North Facade - 2019-02-22
2019-02-22 - Approved General Elevation - South Facade - 2019-02-22
2019-02-22 - Approved General Elevation - West Facade - 2019-02-22
2019-02-22 - Approved General Site Plan - 2019-02-22
2019-02-22 - Approved Grading Plan - 2019-02-22
2019-02-22 - Approved Landscape Plan - 2019-02-22
2019-02-22 - Approved Site Plan - 2019-02-22
2019-02-22 - Approved Site Servicing Plan - 2019-02-22
2019-02-22 - Approved Stormwater Management Plan - 2019-02-22
2019-02-22 - Decision Letter - 2019-02-22
2019-02-22 - Signed DAR - 2019-02-22
2018-02-14 - Application Summary - 2018-02-14
2018-02-08 - - 1st Sub - EC 2018-01-24
2018-02-08 - - 1st Sub - EX1 2018-01-24
2018-02-08 - - 1st Sub - GP 2018-01-24
2018-02-08 - - 1st Sub - Site Servicing and SWM Report 2018-01-24
2018-02-08 - - 1st Sub - SSP 2018-01-24
2018-02-08 - - 1st Sub - SWM 2018-01-24
2018-02-08 - - 1st Sub - Geotech Report 2017-12-22
2018-02-08 - - 1st Sub - Noise Report 2017-12-22
2018-02-08 - - 1st Sub - TCR 2017-12-22
2018-02-08 - - 1st Sub - Transportation Study 2017-12-22
2018-02-08 - - 1st Sub - Elevations 2017-12-21
2018-02-08 - - 1st Sub - Garage Plans 2017-12-21
2018-02-08 - - 1st Sub - Ground Floor 2017-12-21
2018-02-08 - - 1st Sub - Landscape Plan 2017-12-21
2018-02-08 - - 1st Sub - Shadow Analysis 2017-12-21
2018-02-08 - - 1st Sub - Site Plan 2017-12-21
2018-02-08 - - 1st Sub - TCR Plan 2017-12-21
Planning Rationale and Design Brief 2017-12-21
2018-02-08 - - 1st Sub - Wind Study 2017-12-19
2018-02-08 - - 1st Sub - ESA 2017-12-11
Date Status
2019-06-07 Agreement Registered - Final Legal Clearance Given
2019-04-05 Receipt of Agreement from Owner Pending
2019-02-22 Request for Agreement Received
2019-02-21 Application Approved
2019-02-20 Councillor Concurs
2018-02-13 Community "Heads Up" - Completed