D07-12-17-0144

Site Plan Control: The City of Ottawa has received a Site Plan Control application to permit the development of a six-storey building (future Sprott School of Business) on the Carleton University campus. View application on ottawa.ca

WardWard 17 - CAPITAL - David Chernushenko
Received2017-11-07
Updated2018-09-13
Address (Zoning) 1125 COLONEL BY (I2A F(1.5))
Possibly related devapp(s) D07-12-13-0053 - Site Plan Control
D07-12-15-0079 - Site Plan Control
D07-12-15-0119 - Site Plan Control
D07-12-16-0191 - Site Plan Control
Documents
Title Modified
2018-06-04 - Decision Letter - 2018-06-04
2018-06-04 - Delegated Authority Report APPROVED - 2018-06-04
2018-06-04 - Exterior Elevation South APPROVED - 2018-06-04
2018-06-04 - Exterior Elevaton East APPROVED - 2018-06-04
2018-06-04 - Exterior Elevaton North-West APPROVED - 2018-06-04
2018-06-04 - Exterior Eleveation South-West APPROVED - 2018-06-04
2018-06-04 - Grading Plan APPROVED - 2018-06-04
2018-06-04 - Landscape Details APPROVED - 2018-06-04
2018-06-04 - Landscape Plan APPROVED - 2018-06-04
2018-06-04 - Level 5 Floor Plan APPROVED - 2018-06-04
2018-06-04 - Removals and Site Servicing Plan APPROVED - 2018-06-04
2018-06-04 - Roof Plan APPROVED - 2018-06-04
2018-06-04 - Site Plan APPROVED - 2018-06-04
2018-06-04 - Stormwater Management Plan APPROVED - 2018-06-04
Roof Drain Memo Approved 2018-05-07
Servicing Report Approved 2018-05-06
2017-11-20 - Application Summary - 2017-11-20
2017-11-20 - Architectural & Engineering Plans - 2017-11-20
2017-11-20 - ESA - Phase I - 2017-11-20
2017-11-20 - Geotechnical Investigation - 2017-11-20
2017-11-20 - Location Map - 2017-11-20
2017-11-20 - Noise & Vibration Study - 2017-11-20
2017-11-20 - Planning Rationale - 2017-11-20
2017-11-20 - Servicing & SWM Report - 2017-11-20
2017-11-20 - Shear Wave Velocity Report - 2017-11-20
2017-11-20 - Transportation Brief - 2017-11-20
Phase I ESA Approved 2017-11-10
Noise & Vibration Study Approved 2017-05-26
Geotechnical Report Approved 2017-03-07
Date Status
2018-09-12 Receipt of Agreement from Owner Pending
2018-06-22 Request for Agreement Received
2018-05-29 Application Approved
2018-05-28 Councillor Concurs
2018-05-24 Applicant Concurs
2018-05-16 Draft Report Sent to Councillor and Applicant for Response
2017-12-19 Comment Period has Ended/Issue Resolution
2017-11-21 Comment Period in Progress
2017-11-14 Community "Heads Up" - Completed

comments powered by Disqus
Created by Kevin O'Donnell to make it easier to be part of the political conversation in Ottawa.
On Twitter? Follow @OttWatch and @ODonnell_K
Privacy Policy