D07-12-17-0069

Site Plan Control: A Site Plan Control application to construct three mixed-use high-rise buildings with residential towers ranging in height up to 35-storeys and a mix of uses on the ground floor and within the podium. The development also includes an urban park, underground parking, and a mid-block pedestrian pathway. View application on ottawa.ca

WardWard 14 - SOMERSET - Catherine Mckenney
Received2017-06-01
Updated2020-09-15
Address (Zoning) 400 ALBERT (R5Q[242] S89A S89B h1 h2)
388 ALBERT (R5Q[240] H(64) S93)
156 LYON (R5Q[240] H(64) S93)
160 LYON (R5Q[240] H(64) S93)
Possibly related devapp(s) D02-02-15-0044 - Zoning By-law Amendment
D07-12-15-0145 - Site Plan Control
D02-02-17-0053 - Zoning By-law Amendment
D02-02-18-0061 - Zoning By-law Amendment
D07-05-19-0004 - Demolition Control
Documents
Title Modified
2020-09-11 - Application Summary and Location Map - 2020-09-14
2020-09-11 - Architectural Plans - 2020-09-14
2020-09-11 - Civil Engineers Plans - 2020-09-14
2020-09-11 - Geotechnical Study and Preliminary Hydrogeological - 2020-09-14
2020-09-11 - HydroGeological Report - 2020-09-14
2020-09-11 - Landscape Plans - 2020-09-14
2020-09-11 - Noise Study - 2020-09-14
2020-09-11 - Phase II ESA - 2020-09-14
2020-09-11 - Servicing and Stormwater Management Report - 2020-09-14
2020-09-11 - Shadow Study - 2020-09-14
2020-09-11 - Survey 156 and 160 Lyon - 2020-09-14
2020-09-11 - Survey 388 and 400 Albert - 2020-09-14
2020-09-11 - Transportation Impact Statement - 2020-09-14
2020-09-11 - Wind Study - 2020-09-14
2020-09-11 - Windy Study Addendum - 2020-09-14
2017-07-07 - Application Summary - 2017-06-30
2017-07-07 Floor Plans 2017-06-30
2017-07-07 Details Plan 2017-06-26
2017-07-07 Grading Plan 2017-06-26
2017-07-07 Ponding Plan 2017-06-26
2017-07-07 Site Servicing Plan 2017-06-26
2017-07-07 Stormwater Management and Site Servicing Plan 2017-06-26
2017-07-07 TA 1 of 2 2017-06-26
2017-07-07 TA 2 of 2 2017-06-26
2017-07-07 Planning Rationale 2017-06-01
2017-07-07 Environmental Impact Statement 2017-05-31
2017-07-07 Geotechnical Study 2017-05-29
2017-07-07 Hydrogeological Analysis 2017-05-29
2017-07-07 Phase II ESA 2017-05-29
2017-07-07 RENDER 1 2017-05-24
2017-07-07 RENDER 2 2017-05-24
2017-07-07 RENDER 3 2017-05-24
2017-07-07 RENDER 4 2017-05-24
2017-07-07 RENDER 5 2017-05-24
2017-07-07 Site Plan 2017-05-19
2017-07-07 PARKING LEVEL 1 2017-05-17
2017-07-07 PARKING LEVEL 2 2017-05-17
2017-07-07 PARKING LEVEL 3 2017-05-17
2017-07-07 PARKING LEVEL 4 2017-05-17
2017-07-07 Sun Shadow Study 2017-05-12
2017-07-07 Community Transportation Study 2017-05-05
2017-07-07 Noise Study 2017-04-20
2017-07-07 Wind Study 2017-04-20
2017-07-07 Landscape Plan 2017-04-03
2017-07-07 Elevations 1 2017-03-17
2017-07-07 Elevations 2 2017-03-17
2017-07-07 Phase I ESA 2017-03-16
2017-07-07 Survey Plan 2016-08-16
Date Status
2020-09-14 Comment Period in Progress
2020-09-08 Revision Request Received
2020-09-03 Application Reactivated
2017-09-08 Application File Pending
2017-07-07 Comment Period in Progress
2017-06-30 Community "Heads Up" - Completed