D07-12-17-0041

Site Plan Control: The proposal is for the construction of 4 buildings; two mixed-use high rise buildings fronting onto Carling Avenue, and two mid-rise residential buildings fronting onto the adjacent local side streets. View application on ottawa.ca

WardWard 16 - RIVER - Riley Brockington
Received2017-04-12
Updated2019-01-24
Address (Zoning) 1354 CARLING (AM10[2518] S389)
1376 CARLING (AM10[2519] S389-h)
Possibly related devapp(s) D02-02-17-0030 - Zoning By-law Amendment
Documents
Title Modified
Community Transportation Study Addendum - 2019-01-22
Geotechnical Study - 2019-01-22
Pedestrian Level Wind Study - 2019-01-22
Phase 1 ESA - 2019-01-22
Planning Rationale - 2019-01-22
Planning Rationale Addendum No1 - 2019-01-22
Sun Shadow Study - 2019-01-22
Archibald and Meath Street Ultimate Closures Functional Plan - 2019-01-16
Archibald Street Closure (Interim) - 2019-01-16
Archibald Street Closure (Ultimate) - 2019-01-16
Conserved Vegetation - 2019-01-16
Current Vegetation Plan - 2019-01-16
East Elevation Ph 1 Archibald Building - 2019-01-16
East Elevation Ph 1 Carling Building - 2019-01-16
Erosion and Sediment Control Plan - 2019-01-16
Existing Conditions and Removals - 2019-01-16
Grading Plan - 2019-01-16
Landscape Details Plan L3_1 - 2019-01-16
Landscape Details Plan L3_2 - 2019-01-16
Landscape Details Plan L3_3 - 2019-01-16
Landscape Details Plan L3_4 - 2019-01-16
Landscape Site Plan - 2019-01-16
Meath Street Closure (Interim) - 2019-01-16
Meath Street Closure (Ultimate) - 2019-01-16
North Elevation Ph 1 Archibald Building - 2019-01-16
North Elevation Ph 1 Carling Building - 2019-01-16
Overall Concept Plan - 2019-01-16
Parking Garage (Level 1 Archibald Building) - 2019-01-16
Parking Garage (Level 1 Carling Building) - 2019-01-16
Parking Garage (Level 2 Carling Building) - 2019-01-16
Planting Plan - 2019-01-16
Site Plan - 2019-01-16
Site Servicing Plan - 2019-01-16
South Elevation Ph 1 Archibald Building - 2019-01-16
South Elevation Ph 1 Carling Building - 2019-01-16
Stormwater Management Plan - 2019-01-16
Tree Inventory List - 2019-01-16
West Elevation Ph 1 Archibald Building - 2019-01-16
West Elevation Ph 1 Carling Building - 2019-01-16
Archibald and Meath Street Closure Functional Design - 2019-01-03
Archibald and Meath Street Closures Design - 2019-01-03
Noist Study - 2019-01-03
Site Servicing Plan Rev 3 - 2018-12-13
Building D and E Renderings Revision 3 - 2018-12-07
Functional Servicing Report - 2018-12-06
Functional Servicing Report Rev 3 - 2018-12-06
Site Grading Plan Rev 3 - 2018-12-06
Stormwater Management Plan Rev 3 - 2018-12-06
Building D garage and elevation plans Revision 3 - 2018-12-04
Building E garage and elevation plans Revision 3 - 2018-12-04
Landscape Plan Rev 3 - 2018-12-04
Site Plan Rev 3 - 2018-12-04
2018-09-10 - Archibald Street Closure - 2018-10-09
2018-09-10 - Meath Street Closure - 2018-10-09
2018-04-30 - Concept Plan Revision 1 - 2018-04-24
2018-04-30 - Planning Rationale Revision 1 - 2018-04-24
2018-04-30 - Wind Study Revision 1 - 2018-04-24
2018-04-30 - Building E Ground Floor - 2018-04-23
2018-04-30 - Community Transportation Study Revision 1 - 2018-04-20
2018-04-30 - Noise Study Revision 1 - 2018-04-20
2018-04-30 - Sun Shadow Study Revision 1 - 2018-04-20
2017-12-06 - 2nd Submission Design Brief - 2017-12-06
Community Transportation Study - 2017-06-29
2017-05-16 - Building Elevations - 2017-05-16
2017-05-16 - Community Transportation Study - 2017-05-16
2017-05-16 - Concept Plan - 2017-05-16
2017-05-16 - Erosion and Sediment Control Plan (plan only) - 2017-05-16
2017-05-16 - Existing Conditions Plan - 2017-05-16
2017-05-16 - Geotechnical Study - 2017-05-16
2017-05-16 - Grade Control and Drainage Plan - 2017-05-16
2017-05-16 - Landscape Plan - 2017-05-16
2017-05-16 - Noise-Vibration Study - 2017-05-16
2017-05-16 - Phase 1 Environmental Site Assessment - 2017-05-16
2017-05-16 - Phase 1 Renderings - 2017-05-16
2017-05-16 - Phase 1 Site Plan - 2017-05-16
2017-05-16 - Phase 2 Environmental Site Assessment - 2017-05-16
2017-05-16 - Planning Rationale - 2017-05-16
2017-05-16 - Proposal Summary - 2017-05-16
2017-05-16 - Servicing Options Report - 2017-05-16
2017-05-16 - Site Renderings - 2017-05-16
2017-05-16 - Site Servicing Plan - 2017-05-16
2017-05-16 - Stormwater Site Management Report (plan) - 2017-05-16
2017-05-16 - Sun Shadow Study - 2017-05-16
2017-05-16 - Tree Conservation Report - 2017-05-16
2017-05-16 - Wind Study - 2017-05-16
2017-05-16- Parking Garage Layout - 2017-05-16
Date Status
2019-12-05 Application Reactivated
2019-01-15 Application Approved
2019-01-03 Draft Report Sent to Councillor and Applicant for Response
2017-07-04 Application File Pending
2017-05-17 Comment Period in Progress
2017-05-02 Community "Heads Up" - Completed

comments powered by Disqus
Created by Kevin O'Donnell to make it easier to be part of the political conversation in Ottawa.
On Twitter? Follow @OttWatch and @ODonnell_K
Privacy Policy