D07-12-15-0062

Site Plan Control: The applicant wishes to make changes to the approved Site Plan for June 2012 to accommodate tenant changes at the Heron Gate Shopping Centre. View application on ottawa.ca

WardWard 18 - ALTA VISTA - Jean Cloutier
Received2015-03-31
Updated2016-07-11
Address (Zoning) 1670 HERON (*_GM F(1.0))
Documents
Title Modified
_Application Summary_Bilingual 2016-07-11
5th Submission_DSEL Memo Storm Management 2016-05-17
5th Submission_Existing Conditions Removals Plan 2016-05-17
5th Submission_Grading Plan 2016-05-17
5th Submission_Sediment & Erosion Control Plan 2016-05-17
5th Submission_Site Servicing Plan 2016-05-17
5th Submission_Electrical Plan 2016-05-16
5th Submission_Electrical Specifications 2016-05-16
5th Submission_Elevations_Bldg A_1 2016-05-16
5th Submission_Elevations_Bldg A_2 2016-05-16
5th Submission_Elevations_Bldg A_3 2016-05-16
5th Submission_Landscape Details_Bldg A & E 2016-05-16
5th Submission_Landscape Plan 2016-05-16
5th Submission_Lighting Layout 2016-05-16
5th Submission_Site Plan 2016-05-16
5th Submission_Transportation Addendum 2016-05-16
_Third Submission_SP 2016-03-08
_3rd Submission_Electrical Diagram 2016-02-29
_Third Submission_DSEL Memo 2016-02-29
_Third Submission_Elevations Blding E 2016-02-29
_Third Submission_Erosion Control Plan 2016-02-29
_Third Submission_Existing Conditions Plan 2016-02-29
_Third Submission_Lighting Layout 2016-02-29
_Third Submission_LP Blding A & E 2016-02-29
_Third Submission_Site Servicing Plan 2016-02-29
_Third Submission_SWM Plan 2016-02-29
_Second Submission_Site Plan 2016-01-21
_Second Submission_Site Plan w Overlay on Previous Submission 2016-01-21
_Second Submission_Erosion Control Plan 2016-01-20
_Second Submission_Existing Conditions Plan 2016-01-20
_Second Submission_Grading Plan 2016-01-20
_Second Submission_Site Service Plan 2016-01-20
_Second Submission_Stormwater Memo 2016-01-20
_Second Submission_Transportation Overview Addendum 2016-01-20
_Second Submission_Electrical Plan 2016-01-19
_Second Submission_Landscape Details 2016-01-19
_Second Submission_Landscape Plan Bldgs A & E 2016-01-19
_Second Submission_Lighting Plan 2016-01-19
_Second Submission_Elevation 2 Bldg A 2015-12-01
_Second Submission_Elevation 3 Bldg A 2015-12-01
_Second Submission_Elevation Bldg E 2015-12-01
_Second Submission_Elevations 1 Bldg A 2015-12-01
_Second Submission_Remedian Excavation Report 2015-11-17
_Second Submission_Infiltration Galleries Memo 2015-10-30
_Second Submission_Site Lighting Letter 2015-10-29
_Transportation Addendum #5_Submitted May 1, 2015 2015-05-01
1670 Heron Road_Location Map 2015-04-10
_DSEL Memo 2015-03-30
_Electrical Details 2015-03-30
_Erosion 2015-03-30
_Grading 2015-03-30
_Landscape Details Bldings A and E 2015-03-30
_Landscape Plan Blding A and E 2015-03-30
_Planning Rationale 2015-03-30
_Site Plan Lighting Layout 2015-03-30
_Site Servicing Plan 2015-03-30
_SP 2015-03-26
_Blding A East Elevation 2015-03-25
_Blding A North & South Elevation 2015-03-25
_Blding A West Elevation 2015-03-25
_Confirmation of Remedial Measures 2015-03-24
_Elevation Building E 2015-03-24
_Geotech 2015-03-24
_Noise Study Update 2015-03-24
_Remediation Report 2015-03-24
_Transportation Overview Addendum 2015-03-24
Plan 4R-26407 2015-03-24
Date Status
2016-07-08 Request for Agreement Received
2016-05-10 Application File Pending
2016-03-09 Application Reactivated
2015-05-26 Application File Pending
2015-05-21 Comment Period has Ended/Issue Resolution
2015-04-14 Comment Period in Progress

comments powered by Disqus