D02-02-18-0089

Zoning By-law Amendment: A Site Plan Control application has been submitted in order to construct four residential towers on two parcels. On the northern parcel, the proposal intends to contruct Tower 3 and Tower 4 of Petrie's Landing I, at heights of 22 floors and 18 floors, respectively. The southern parcel is to contain Tower 5a and 5b of Petrie's Landing I, at heights of 32 and 22 floors, respectively. A Rezoning application has been submitted to permit an increased maximum height for Tower 3 from the permitted 109.4m above sea-level (A.S.L.) to 127.9m A.S.L. and for Tower 4 from the permitted 109.4m A.S.L. to 113.1m A.S.L.. A maximum height increase has also been requested for Tower 5a & 5b from the permitted 101m to 158m and 127.9m, respectively. The Zoning By-law Amendment application also seeks permission to allow various commercial uses be permitted on the ground floor of Towers 5a and 5b, in order to provide a mixed-use building on the site & a reduction in minimum parking requirements for 5a & 5b View application on ottawa.ca

WardWard 1 - ORLÉANS - Bob Monette
Received2018-09-24
Updated2018-10-29
Address (Zoning) 8900 JEANNE D'ARC (R5A H(101) A.S.L.)
Possibly related devapp(s) D07-12-13-0248 - Site Plan Control
D02-02-14-0126 - Zoning By-law Amendment
D01-01-14-0025 - Official Plan Amendment
D07-12-18-0143 - Site Plan Control
Documents
Title Modified
2018-10-12-Transportation Impact Assessment- 2018-10-29
2018-10-12-Wind Study- 2018-10-29
2018-10-12-Site Plans- 2018-10-29
2018-10-12-Topographical Survey- 2018-10-29
2018-10-12-Traffic Noise Study- 2018-10-29
2018-10-12-Phase One ESA- 2018-10-29
2018-10-12-Planning Rationale- 2018-10-29
2018-10-12-Shadow Study- 2018-10-29
2018-10-12-Archaeological Assessment- 2018-10-29
2018-10-12-Design Brief- 2018-10-29
1st Submission Phase One Environmental Site Assessment 2018-10-24
2018-10-24 - Application Summary - 2018-10-24
2018-10-24 - Survey plan - 2018-10-24
1st Submission Topographical Survey 2018-10-11
1st Submission Environmental Impact Statement & Tree Conservation Report 2018-09-24
2018-10-12 - EIS & Tree Conservation Report - 2018-09-24
1st Submission Urban Design Brief 2018-09-18
1st Submission Geotechnical Investigation 2018-09-14
2018-10-12 - Geotechnical Investigation - 2018-09-14
1st Submission Landscape Plan 1 2018-09-12
1st Submission Landscape Plan 2 2018-09-12
2018-10-12 - Landscape Plan 1 - 2018-09-12
2018-10-12 - Landscape Plan 2 - 2018-09-12
1st Submission Site Plans & Drawings 2018-09-11
1st Submission Transportation Impact Assessment Strategy Report 2018-08-20
1st Submission Planning Rationale 2018-08-16
1st Submission Pedestrian Level Wind Study 2018-07-18
1st Submission Shadow Impact Study 2018-07-18
1st Submission Traffic Noise Assessment 2018-07-18
1st Submission 4R-24089 2017-10-10
1st Submission Stage 1 & 2 Archaeological Assessment 2013-12-16
Date Status
2018-10-25 Comment Period in Progress
2018-10-22 Community "Heads Up" - Completed