D02-02-18-0057

Zoning By-law Amendment: 11 storey residential View application on ottawa.ca

WardWard 8 - COLLEGE - Rick Chiarelli
Received2018-05-29
Updated2019-11-20
Address (Zoning) 2140 BASELINE (MC[2588] F(4.4) H(45))
Possibly related devapp(s) D07-12-18-0084 - Site Plan Control
Possibly related by-laws 2017-360: A by-law of the City of Ottawa to close a portion of the road allowance adjacent to lands municipally known as 2140 Baseline Road, City of Ottawa.
Documents
Title Modified
2019-01-07 - - Erosion and Sediment Control Plan 2019-10-31
2019-01-07 - - Existing Conditions Plan 2019-10-31
2019-01-07 - - Grading Plan 2019-10-31
2019-01-07 - - Landscape Plan 2019-10-31
2019-01-07 - - Planning Rationale Addendum 2019-10-31
2019-01-07 - - Servicing and Stormwater Report 2019-10-31
2019-01-07 - - Site Servicing Plan 2019-10-31
2019-01-07 - - views, elevations, floor plans, site plan 2019-10-31
2019-07-16 - Second Submission Existing Conditions and Removals Plan - 2019-10-31
2019-07-16 - Second Submission Grading Plan - 2019-10-31
2019-07-16 - Second Submission Sediment and Erosion Plan - 2019-10-31
2019-07-16 - Second Submission Site Servicing Plan - 2019-10-31
2019-07-16 - Second Submission Storm Drainage Area Plan - 2019-10-31
2019-07-16 - Second Submission Stormwater and Servicing Management Report - 2019-10-31
2018-07-06 - Application Summary - 2018-07-06
2018-07-13 - - UDRP Presentation 2018-06-21
2018-06-27 - - Planning Rationale 2018-06-06
2018-06-27 - - Transportation Impact Assessment 2018-06-05
2018-06-27 - - Traffic Noise Assessment 2018-05-28
2018-06-27 - - Tree Conservation Report 2018-05-28
2018-06-27 - - Engineering Plan C1 2018-05-25
2018-06-27 - - Engineering Plan C2 2018-05-25
2018-06-27 - - Landscape Plan 2018-05-25
2018-06-27 - - Servicing and Stormwater Management Report 2018-05-25
2018-06-27 - - Site Plan, Elevations, Sections, Floor Plans 2018-05-25
2018-06-27 - - Tree Conservation Plan 2018-05-25
2018-06-27 - - Geotechnical Report 2018-01-15
2018-06-27 - - Phase 1 Environmental Site Assessment 2018-01-15
2018-06-27 - - Phase 2 Environmental Site Assessment 2018-01-15
Date Status
2019-11-18 Zoning By-law in Effect
2019-10-29 By-law Passed - In Appeal Period
2018-07-27 Community "Heads Up" - Completed
2018-07-06 Comment Period in Progress

comments powered by Disqus
Created by Kevin O'Donnell to make it easier to be part of the political conversation in Ottawa.
On Twitter? Follow @OttWatch and @kevinodotnet
Privacy Policy