D02-02-16-0053

Zoning By-law Amendment: The City of Ottawa has received a Zoning By-law Amendment application to permit an 8-storey mixed-use building with ground floor commercial uses and a 160 unit retirement residence. An underground parking garage with 54 vehicle parking spaces is proposed to be accessed from Monk Street. View application on ottawa.ca

WardWard 17 - CAPITAL - David Chernushenko
Received2016-07-12
Updated2017-02-13
Address (Zoning) 890 BANK (*_TM H(15))
900 BANK (*_TM H(15))
Possibly related devapp(s) D07-12-14-0110 - Site Plan Control
Possibly related by-laws 2017-133: A by-law of the City of Ottawa to amend By-law No. 2008-250 of the City of Ottawa to change the zoning of lands known municipally as 890 and 900 Bank Street
Documents
Title Modified
2017-01-30 - Traffic Volumes - 2017-02-08
2017-01-30 - 1st Floor Plan - 2017-01-30
2017-01-30 - 2nd Floor Plan - 2017-01-30
2017-01-30 - 3rd Floor Plan - 2017-01-30
2017-01-30 - 4th Floor Plan - 2017-01-30
2017-01-30 - 5th Floor Plan - 2017-01-30
2017-01-30 - 6th Floor Plan - 2017-01-30
2017-01-30 - 7th Floor Plan - 2017-01-30
2017-01-30 - 8th Floor Plan - 2017-01-30
2017-01-30 - Building Section A - 2017-01-30
2017-01-30 - Building Section B - 2017-01-30
2017-01-30 - Building Section C - 2017-01-30
2017-01-30 - Building Section D - 2017-01-30
2017-01-30 - P1 Floor Plan - 2017-01-30
2017-01-30 - Rationale - 2017-01-30
2017-01-30 - Site Plan - 2017-01-30
2017-01-30 - Street Renderings - 2017-01-30
2017-01-30 - Suite Mix - 2017-01-30
January 2017 - - Building Section A West-East 2017-01-18
January 2017 - - 8-9-10am DST Shadow Study 2017-01-16
January 2017 - - Parking Memo 2017-01-16
January 2017 - - Succession Dev'l Letter on Parking 2017-01-16
December 2016 - - UDRP Formal Recommendations 2016-12-19
December 2016 - - Response to Letter from Glebe Community Association 2016-12-07
December 2016 - - Elevations 2016-12-06
December 2016 - - Transportation Memorandum 2016-12-06
December 2016 - - Floor Plans 2016-12-05
December 2016 - - Planning Rationale 2016-12-05
December 2016 - - Site Plan 2016-12-01
December 2016 - - Transportation Brief 2016-12-01
november 2016 - - UDRP Applicant Project Summary Sheet 2016-11-28
november 2016 - - UDRP Formal Design Brief 2016-11-28
august 2016 - - geotechnical addendum 2016-08-10
august 2016 - - public services assessment 2016-08-10
august 2016 - - wind study 2016-08-10
august 2016 - - shadow study 2016-07-12
august 2016 - - transportation brief 2016-07-12
august 2016 - - planning rationale 2016-07-11
august 2016 - - elevations 2016-07-08
august 2016 - - noise study 2016-07-08
august 2016 - - geotechnical study 2016-06-24
august 2016 - - floor plans 2016-06-15
august 2016 - - plan of survey 2014-05-13
Date Status
2017-01-30 Application Reactivated
2016-12-05 Application Reactivated
2016-08-18 Comment Period in Progress