D01-01-14-0020

Official Plan Amendment: The Official Plan Amendment proposes to introduce a site-specific exception policy that would allow buildings up to 27 and 32 storeys in the Official Plan. This proposal will have a five-storey podium, and three levels of underground parking. The first two floors of the podium would consist of retail uses, with the remaining three as structured parking, while the towers would consist of residential units. View application on ottawa.ca

WardWard 12 - RIDEAU-VANIER - Mathieu Fleury
Received2014-08-22
Updated2017-03-17
Address (Zoning) 151 CHAPEL (TM[2339] F(6.0) S354)
153 CHAPEL (TM[2339] F(6.0) S354)
Possibly related devapp(s) D02-02-14-0107 - Zoning By-law Amendment
D07-12-15-0087 - Site Plan Control
Documents
Title Modified
Resubmission April 2015 2015-04-20
CTS Addendum 1 April 2015 2015-04-16
Master Plan Studies April 2015 2015-04-15
Architectural Plans April 2015 2015-04-10
Phase 2 ESA 2014-09-03
Design Concept Summary 2014-08-28
Planning Rationale 2014-08-28
Wind Study 2014-08-28
Noise Study 2014-08-26
Transportation Study 2014-08-26
Context & Project Stats 2014-08-13
Floorplans & Elevations 2014-08-13
Site Plan 2014-08-11
Sun Shadow Study 2014-08-09
Geotechnical Report 2014-07-30
Adequacy of Existing Services 2014-07-25
Survey Plan 2014-06-11
Phase 1 ESA 2013-04-12
Date Status
2016-04-26 Application Approved by OMB
2015-04-10 Appealed to OMB
2014-10-30 Application on Hold
2014-09-23 Comment Period in Progress